ORANGE COUNTY, Fla. – Crews are on track to complete the I-4 Ultimate project by the end of the year, according to the Florida Department of Transportation.
FDOT said this past December, crews finished the final alignment of general-use lanes.
Recommended Videos
This has increased safety on the corridor, drivers will experience fewer lane closures and lane shifts in 2021, according to FDOT.
[TRENDING: Woman arrested in hit-run involving sheriff | Gov: Fla. won’t require ‘vaccine passports’ | Girl missing for weeks]
Transportation officials said crews will finish managed lanes in 2021.
Crews will also have to put down the final layer of asphalt, which will complete the paving process on the 21-mile project.
The project goes from State Road 434 to Kirkman Road.
The estimated cost of the project is about $2.3 billion.
Drivers can view a construction schedule and lane closure schedule at this link from the FDOT.
ClickOrlando.com previously reported that the cost of the project was $4.5 billion. We regret the error.